SCE civil project proof · Blackbutt, NSW

Pavement Reconstruction at Blackbutt

A recorded civil pavement project involving deep excavation, lime stabilisation, pavement-layer reconstruction, stormwater adjustments, kerbs, landscaping and line marking.

Pavement removal and asphalt resurfacing during SCE's Blackbutt NSW reconstruction project
The available page-specific image records pavement removal and asphalt treatment during the Blackbutt works.

Project overview

Rebuilding a deteriorated pavement corridor

The existing project record documents remediation of deteriorated pavement at Blackbutt, with the delivery sequence reorganised from an initial five-stage approach into two recorded work stages. This page remains project proof and directs broader enquiries to the relevant Civil Services owners.

Location

Blackbutt, NSW

A regional pavement-reconstruction setting with staging, access and existing-infrastructure constraints.

Project type

Civil pavement reconstruction

Subgrade and pavement-layer work supported by drainage, kerb, landscaping and line-marking activities.

Delivery record

Two-stage works sequence

The existing project record states that an initial five-stage plan was reorganised into two work stages.

Recorded scope

Work across the pavement build-up and streetscape

  • Project assessment, planning and surface preparation.
  • Excavation of existing pavement to a recorded depth of 1.5 metres below subbase level.
  • Lime stabilisation of the existing subgrade and backfill material.
  • Preparation and grading of subbase and base-course layers.
  • Installation of flexible pavement.
  • Adjustment of the existing stormwater system and reconstruction of kerbs.
  • Street landscaping, line marking and recorded quality-assurance activities.

Delivery approach

Coordinating staging, pavement layers and existing services

The project record identifies staging coordination, lime stabilisation and the integration of stormwater, kerb, landscaping and line-marking work as key delivery considerations. These activities required the pavement sequence to be coordinated around existing conditions and the recorded two-stage programme.

The existing record also notes compaction testing, survey checks and quality records as part of the delivery and handover process.

Recorded outcome

Reconstructed pavement and supporting works

The recorded delivery comprised reconstructed pavement layers together with kerb, stormwater, landscaping and line-marking works. No performance guarantee or unverified regulatory claim is made on this project-proof page.

Frequently asked questions

Blackbutt pavement reconstruction

What work was recorded for the Blackbutt pavement project?

The recorded scope included assessment and preparation, deep pavement excavation, lime stabilisation, subbase and base-course work, flexible pavement, stormwater adjustments, kerb reconstruction, landscaping, line marking and quality-assurance activities.

How was the Blackbutt project staged?

The existing project record states that an initial five-stage approach was reorganised into two recorded work stages.

What pavement layers and treatments were included?

The recorded work included lime stabilisation of existing subgrade and backfill, preparation and grading of subbase and base-course layers, and installation of flexible pavement.

Were drainage, kerbs and line marking included?

Yes. The existing record includes adjustment of the stormwater system, kerb reconstruction, street landscaping and line marking within the project scope.

Where can I see related civil infrastructure projects?

Visit SCE's Civil Infrastructure Projects collection for related project evidence.

Planning pavement reconstruction or road civil works?

Share the site location, available drawings, pavement condition, access constraints and intended programme with SCE for an initial project discussion.