Blackbutt, NSW
A regional pavement-reconstruction setting with staging, access and existing-infrastructure constraints.
SCE civil project proof · Blackbutt, NSW
A recorded civil pavement project involving deep excavation, lime stabilisation, pavement-layer reconstruction, stormwater adjustments, kerbs, landscaping and line marking.
Project overview
The existing project record documents remediation of deteriorated pavement at Blackbutt, with the delivery sequence reorganised from an initial five-stage approach into two recorded work stages. This page remains project proof and directs broader enquiries to the relevant Civil Services owners.
A regional pavement-reconstruction setting with staging, access and existing-infrastructure constraints.
Subgrade and pavement-layer work supported by drainage, kerb, landscaping and line-marking activities.
The existing project record states that an initial five-stage plan was reorganised into two work stages.
Recorded scope
Delivery approach
The project record identifies staging coordination, lime stabilisation and the integration of stormwater, kerb, landscaping and line-marking work as key delivery considerations. These activities required the pavement sequence to be coordinated around existing conditions and the recorded two-stage programme.
The existing record also notes compaction testing, survey checks and quality records as part of the delivery and handover process.
The recorded delivery comprised reconstructed pavement layers together with kerb, stormwater, landscaping and line-marking works. No performance guarantee or unverified regulatory claim is made on this project-proof page.
Related pathways
Explore the matching project collection, road-delivery pathways and SCE's controlled project system.
Frequently asked questions
The recorded scope included assessment and preparation, deep pavement excavation, lime stabilisation, subbase and base-course work, flexible pavement, stormwater adjustments, kerb reconstruction, landscaping, line marking and quality-assurance activities.
The existing project record states that an initial five-stage approach was reorganised into two recorded work stages.
The recorded work included lime stabilisation of existing subgrade and backfill, preparation and grading of subbase and base-course layers, and installation of flexible pavement.
Yes. The existing record includes adjustment of the stormwater system, kerb reconstruction, street landscaping and line marking within the project scope.
Visit SCE's Civil Infrastructure Projects collection for related project evidence.
Share the site location, available drawings, pavement condition, access constraints and intended programme with SCE for an initial project discussion.