Creek access and groundwater
Temporary access and groundwater-management arrangements supported work within the constrained creek-crossing area.
SCE project | civil infrastructure and flood-damaged crossing reconstruction
SCE Corp delivered and coordinated the reconstruction of a flood-damaged creek crossing in Emu Heights, including screw-pile foundations, groundwater management, excavation, reinforced-concrete works, precast box culverts, wing walls and backfilling.
Project overview
Flooding damaged the crossing and road approach, eroding the surfaces and disrupting access. SCE progressed from assessment and temporary site access through foundation, concrete, culvert and backfilling works.
Screw piles formed part of the foundation system. Groundwater-management arrangements and temporary access supported bulk excavation and preparation for the reinforced-concrete base slab. The subsequent sequence included concrete aprons, twin precast box culverts, reinforced wing walls and reconstruction of the approaches.
SCE managed the foundations, excavation, reinforced concrete, culvert installation, wing walls and backfilling as a connected construction programme, coordinating the required project-team and authority inputs.
SCE recommended geotechnical investigation before the foundation approach was finalised. Managing Director Frank MANESH recalls the boreholes encountering rock at approximately one to two metres, shallower than the original foundation assumptions suggested. The investigation gave the design and construction team site evidence to use when reviewing the proposed long piles.
Shallower rock did not remove the groundwater challenge at the creek crossing. SCE brought the geotechnical, design-engineering and construction inputs together to review the foundation approach alongside water conditions, excavation and temporary access. The aim was a design and work sequence that addressed the site as a whole, rather than resolving the bearing conditions while leaving groundwater to be dealt with during construction.
Frank reports that this review produced a more economical foundation approach. The delivered system included steel screw piles, as shown in the construction records below. It demonstrates SCE’s engineering problem-solving approach: investigate a material assumption, involve the relevant disciplines and assess the practical alternative before committing to the work.
Delivery controls
Temporary access and groundwater-management arrangements supported work within the constrained creek-crossing area.
Screw piles, excavation, the reinforced base slab and concrete aprons were progressed in sequence before the culvert and wing-wall stages.
The twin box culverts, wing walls and backfilled approaches were coordinated as connected parts of the reconstructed crossing.
Project photographs
The photographs document the crossing before reconstruction and the principal construction stages through foundations, reinforced concrete, box-culvert installation, wing walls and backfilling.
Project video
The video summarises the project stages from the existing flood damage through foundation, excavation, concrete, culvert, wing-wall and backfilling works.
Completed bridge reconstruction
The structural crossing was reconstructed with twin box culverts, reinforced-concrete wing walls, backfilled approaches and access railing. The photographs show the completed structural stage and the principal construction activities.
Project questions
For related drainage, structural and site-interface decisions, explore our civil drainage and structure questions.
SCE delivered temporary access, groundwater management, screw-pile foundations, bulk excavation, a reinforced-concrete base slab and aprons, twin precast box culverts, reinforced wing walls and backfilling of the approaches.
Steel screw piles formed part of the foundations for the reconstructed creek crossing. SCE recommended ground investigation before finalising the approach. The boreholes identified shallower rock than originally assumed, allowing the design and construction team to review the proposed long piles while also addressing groundwater, excavation and temporary access.
SCE reviewed groundwater alongside the foundation approach, excavation and temporary access, bringing geotechnical, design-engineering and construction inputs together. Groundwater-management arrangements and temporary scaffolded access then supported work within the creek-crossing area. Finding shallower rock did not remove the need to plan for the water conditions.
The works included foundation piles, a reinforced base slab, concrete aprons, twin precast box-culvert units and reinforced-concrete wing walls.
The work progressed through access arrangements and groundwater management, screw piles, excavation, base-slab preparation, concrete aprons, culvert installation, wing-wall construction and backfilling.
The completed structural stage shows the reconstructed box-culvert crossing, concrete wing walls, backfilled approaches and access railing.
SCE integrated the foundation, concrete, culvert and approach works, coordinating access, construction stages and the required design, inspection and authority inputs.
Provide the location, photographs, drawings and reports, water and access conditions, approval information, proposed programme and required works so SCE can assess and plan the project.
Contact SCE with the site location, available drawings and reports, photographs, access constraints, programme and required scope so SCE can assess the site and plan the engineering and construction package.