Site controls, tree removal and earthworks
SCE installed erosion and sediment control measures, removed trees and undertook earthworks. The photo sequence records the sediment barrier, cleared site and ground preparation.
Civil subdivision · Mount Colah NSW
SCE delivered a civil subdivision package in Mount Colah, combining erosion and sediment controls, tree removal, earthworks, retaining wall construction, stormwater installation, sewer relocation, underground services and construction of a suspended driveway.
Rock excavation was a key challenge. The project brought together site preparation, earthworks, drainage, services and access construction within the subdivision works.

The complete scope covered eight connected elements of the civil works.
SCE installed erosion and sediment control measures, removed trees and undertook earthworks. The photo sequence records the sediment barrier, cleared site and ground preparation.
The works included construction of a retaining wall. Photographs show reinforcement preparation and the wall under construction alongside the access route.
SCE installed the stormwater system and relocated the sewer line. These were distinct components of the project’s drainage and servicing scope.
The package included installation of underground services and construction of a suspended driveway. The final access photograph shows the concrete driveway following placement.
Project photographs follow the civil works through site controls, clearing, retaining wall preparation, underground services and driveway construction.
Select a photograph to view it at full size.





Rock excavation was a specific challenge on the Mount Colah subdivision. SCE’s scope combined the earthworks with retaining wall construction, stormwater, sewer relocation, underground services and the suspended driveway. The photographs show the relationship between the access route, adjoining buildings and successive civil work stages.
Explore Civil Infrastructure Projects, Subdivision Services, Mount Colah service information.
The scope included erosion and sediment controls, tree removal, earthworks, retaining wall construction, stormwater installation, sewer line relocation, underground services and construction of a suspended driveway.
Rock excavation was a key challenge. The civil package also covered retaining walls, drainage, sewer relocation, underground services and driveway construction.
Yes. SCE installed the stormwater system, relocated the sewer line, installed underground services and constructed a suspended driveway as part of the subdivision works.
Share the site location, plans, available geotechnical information and proposed civil scope. SCE can review the earthworks, drainage, services and access requirements.