Decluttering across the classrooms included in the refurbishment scope.
Education projects · Cherrybrook
SCE Corp refurbished multiple classrooms at Cherrybrook Technology High School for the Department of Education, bringing together decluttering, plastering, repainting and installation of Autex acoustic panels.
The school-holiday programme required all works to start and finish within two weeks, making construction planning central to the project.

The project combined classroom preparation, plastering and new paint finishes with acoustic wall treatment. SCE managed these works as one refurbishment package across multiple teaching spaces.
Autex acoustic panels formed a distinct part of the scope. The finished photographs show the red wall panels, repainted surfaces and the relationship between the new finishes and the existing classroom layouts.
Decluttering across the classrooms included in the refurbishment scope.
Plastering works to the classroom interiors as part of the coordinated refurbishment.
Repainting of the classroom surfaces included in the agreed works.
Installation of Autex acoustic panels across multiple classrooms, integrated with the plastering and painting work.
The defining constraint was the available work period: all works were to commence and be completed within two weeks of school holidays. Planning had to bring the scope, trade sequence and classroom access into the same programme.
Decluttering, plastering, repainting and panel installation needed to be coordinated across the affected rooms. The project demonstrates SCE’s experience managing several connected refurbishment activities around an education facility’s operational timetable.
Six views of the classroom refurbishment and adjoining circulation areas. Select any photograph to view it at full size.





The main classroom photograph is shown at the top of this page.
This project sits within SCE’s wider government, education and childcare portfolio. Our team brings construction management, building expertise and engineering capability to the planning and delivery of facility upgrades. Our qualifications, registrations and certifications and SCE System support this coordinated approach.
For projects across the region, explore SCE’s Parramatta and Greater West construction services.
Explore our government, education and childcare projects and commercial refurbishment services for related work and delivery capabilities. The Northern Sydney school repair programme provides another example of work across education facilities, while our school repair and childcare refurbishment guide explains the broader planning considerations.
For related questions about scope, budgets, approvals and staging, explore our renovation and fit-out planning questions.
SCE carried out decluttering, plastering, repainting and installation of Autex acoustic panels across multiple classrooms for the Department of Education.
All works were required to commence and be completed within a two-week school-holiday window. Planning the classroom work and coordinating the sequence of trades were central to that requirement.
Autex acoustic panels were installed as part of the classroom refurbishment. The photographs show the red acoustic wall treatment alongside the completed interior finishes.
Identify the rooms, required repairs and finishes, equipment that needs protection or relocation, and the dates when each area is available. Provide photographs, drawings and any known building-condition issues. SCE can then coordinate the technical scope, material selections, procurement and trade sequence, including cleaning, checks and handover before the rooms return to use.
Yes. SCE plans education refurbishment around the facility’s operational requirements and available shutdown period. The Cherrybrook brief required a two-week holiday window, so multiple finishing trades had to be planned together. For a new project, we review access dates, scope, material availability and preparation needs before confirming a workable programme with the school.
Tell us which spaces need upgrading, the work required and your available school-holiday or shutdown window. SCE can assess the scope and plan a coordinated construction programme.