Balmain Apartment Cladding Replacement: Project Video

Watch this 27-second SCE project video documenting rope-access delivery and completed cladding-replacement work associated with the Balmain apartment project.

Balmain apartment cladding-replacement project. Video duration: 27 seconds.

What This Video Shows

The video shows rope-access work and the completed façade on SCE’s Balmain apartment project.

Why was rope access selected?

The Balmain access plan followed a comparison of practical options. The required scaffolding licence could not be obtained, and projecting balconies obstructed the vertical travel needed by a staging system. SCE used rope access to work around the balconies and installed a protective gantry below for debris and falling objects. The full Balmain case study explains the decision; our façade access guide covers planning for another building.

Explore the Balmain project

Read the complete Balmain project record for the façade-replacement scope, rope-access delivery and completion details. Product specifications, design documents and formal compliance records are assessed separately from the video.