Make-safe planning checklist
Make-Safe Planning Checklist for Insurers and Strata in NSW
Make-safe work means temporary action to control immediate risks after building damage, such as securing damaged areas, providing weather protection or installing engineer-designed structural support. This checklist helps insurers, loss adjusters, strata managers and property managers prepare the incident, access and authority information needed to plan that response.
Immediate danger: do not enter an unsafe area. If there is an immediate threat to life or public safety, contact emergency services on 000 and the relevant authority or utility. An SCE enquiry does not guarantee attendance or a particular response time.
Useful first information
Start with four facts you can gather safely
Good initial information helps identify the immediate condition, the authorised decision-makers and the inputs needed before any temporary construction activity is agreed.
Known hazards and access
Identify exclusion zones, affected services, occupants, access restrictions and controls already in place. Do not enter a damaged area to collect information.Authority and contacts
Identify the insurer, loss adjuster, strata or property representative and the person authorised to discuss access, scope and expenditure.Safe-to-obtain records
Share available photographs, incident references, reports, drawings and claim details without exposing anyone to additional risk.Separate the immediate risk from the permanent repair
Make-safe work and permanent rectification answer different questions. Keeping them separate supports clearer scope, records and responsibility.
Immediate make-safe decision
The immediate scope addresses identified risks to people, property and adjoining areas. It may involve temporary protection, structural stabilisation and site controls, with engineering input matched to the damage and proposed work.- Access and exclusion controls
- Temporary weather protection
- Protection around damaged elements
- Engineer-designed temporary support and propping where required
- Securing loose non-structural components where appropriate
Permanent repair pathway
Permanent repairs may require separate investigation, monitoring, design, approval, procurement and construction. These later steps are not implied by a temporary make-safe scope.- Condition assessment and specialist input
- Design or registered-practitioner responsibilities
- Insurance coverage and claim decisions
- Separately authorised repair construction
Make-safe request checklist
The checklist below gives the reviewing team practical information without asking occupants or representatives to inspect unsafe areas.
| Checklist item | What to include | Why it matters |
|---|---|---|
| Incident summary | Address, date, event type, affected area and any continuing change. | Establishes the known condition and urgency. |
| People and access | Occupancy, vulnerable users, site contacts, keys, inductions and access limits. | Supports safe planning and stakeholder coordination. |
| Known hazards | Damaged areas, utilities, loose materials, water, fire, impact or access concerns already identified. | Helps define exclusions and required inputs. |
| Authority to proceed | Authorised contact, insurer or claim reference and approval pathway. | Clarifies who can instruct and accept the agreed scope. |
| Available evidence | Safe photographs, reports, drawings, previous correspondence and relevant site records. | Reduces ambiguity before attendance or scope discussion. |
| Expected handover | Required notes, photographs, limitations, observations and next-step contacts. | Creates a controlled transition to assessment or repair planning. |
How SCE supports a controlled response
SCE manages make-safe planning and construction, bringing together engineering input, temporary structural support, access controls, building protection and incident records. Our qualified team and appointed specialists develop the response around the damage, safe access and authority to proceed, then connect temporary measures with the next stage of investigation or reconstruction.
1. Initial information
Confirm the incident, affected area, known hazards and authorised contacts.2. Access inputs
Review site constraints and the information required from relevant parties.3. Agreed actions
Define the temporary works, engineering requirements, construction sequence and responsibilities.4. Records and handover
Document completed actions, observations and limitations within the agreed scope.5. Next pathway
Identify separately authorised investigation, design, approval or repair steps where required.Choose the right SCE pathway
Explore emergency make-safe services for urgent building risks, insurance response services for claim-related work, and the Villawood project for an example of engineering, temporary support and reconstruction.
Emergency Make-Safe Works
Use this pathway for an urgent building condition requiring review of temporary construction or site-control measures. Explore emergency make-safe worksInsurance Make-Safe Response
Use the insurance-specific pathway for authorised response coordination, site records and claim-supporting handover. Explore insurance make-safe responseVillawood Project Evidence
See SCE’s engineering design, temporary support, authority liaison and brickwork following major vehicle-impact damage. Reconstruction is ongoing. View the Villawood project recordPractical questions