1. Issue one document register
List each current report, drawing, specification, schedule, addendum, approval and instruction by title, number, revision and date. Mark superseded information and identify documents for construction, tender, reference or information only.
2. State design and investigation status
Summarise visual inspection, testing, scanning and opening-up; concealed areas; accepted causes; remaining assumptions; and locations needing confirmation after access. Link defect references and measured quantities to drawings, photographs or schedules. Use the investigation decision guide where the evidence pathway remains unresolved.
3. Define boundaries and interfaces
Show work areas, limits, retained elements, removal, repair or replacement, finishes, protection and reinstatement. Identify waterproofing, façade, structure, fire, hydraulic, electrical, mechanical, landscape, neighbour and occupied-area interfaces. State whether quantities are fixed, measured or provisional.
4. Build a responsibility matrix
For each deliverable, name the party that prepares, reviews, accepts, lodges, installs, inspects and closes it. Cover design, regulated designs, declarations, submissions, samples, temporary works, access engineering, permits, testing, notices, authority interfaces, variations and completion records.
5. Confirm DBP and approvals
For Class 2 remedial work, confirm building class, work type, exclusions relied on, design-practitioner classes, Construction Issued Regulated Design status, declarations, lodgement timing and responsibility. SCE is a DBP-registered building practitioner with qualified building, civil and construction engineering capability. Confirm the appointed building practitioner, designers and declaration responsibilities for the particular works.
6. Align access and staging
Issue work zones, access requirements, occupied-building constraints, emergency egress, work hours, public protection, weatherproofing, temporary support, environmental controls, resident communication and daily handback requirements. Define specialist design inputs and review hold points.
7. Define submittals and hold points
Create a schedule for materials, product data, samples, trials, methodologies, inspection and test plans, temporary works, access plans, shop drawings and warranties. State the evidence required, the authorised release party and the programme consequence.
8. Establish change control
Agree notification, photographs, marked-up location, measurement, technical review, time and price assessment, approval authority and document revision before affected work proceeds. Use the latent conditions checklist after discovery.
9. Define closeout at the start
Set the completion index for approved designs and changes, declarations, product and batch records, inspections, tests, photographs, as-built mark-ups, warranties, maintenance information, defects, training and final acceptance. The remedial closeout guide explains the detailed completion-stage checklist.