Define the outcome
State what must be achieved, where the work occurs and the standard or acceptance criteria that will demonstrate completion.
Construction pricing preparation
A practical construction scope-of-works checklist for giving contractors the same site information, inclusions, constraints, evidence and quote-return requirements.
When one contractor prices a complete work package and another prices only the visible task, the totals cannot be compared fairly. A good scope of works brief gives every tenderer a common baseline and a defined place to disclose assumptions, exclusions and alternatives.
State what must be achieved, where the work occurs and the standard or acceptance criteria that will demonstrate completion.
Provide occupancy, access, known conditions, interfaces, available records and anything that may affect the work method.
List the work, temporary measures, protection, testing and closeout that are included, then state what is expressly outside the package.
Issue current drawings, photographs, reports, schedules and site information with revision and date controls.
Require tenderers to identify qualifications, allowances, provisional items, alternatives, lead times and information still needed.
State inspections, tests, records, warranties, manuals, training, defects steps and the evidence required for completion.
Use the checklist as a briefing structure, then adapt each item to the project, delivery model and work package.
Evidence pack
Words alone may not define a work package. Give tenderers a controlled evidence pack and an index showing what each document is, its revision and whether it is for information, pricing or construction.
Identify limitations openly. If information is preliminary or unverified, say so and require the tenderer to state how that uncertainty has been priced.
A contractor needs more than the site address. The brief should describe the practical route from delivery to workfront and the restrictions that apply along the way.
Where access has not been verified, require a tender inspection and a written list of remaining assumptions rather than allowing each contractor to make a different silent allowance.
Many quote gaps occur between packages. The scope should identify who disconnects, protects, modifies, tests, commissions, makes good and signs off each interface.
| Interface question | What the brief should clarify | What the quote should return |
|---|---|---|
| Existing services | Available records, isolation responsibility, locating requirements, shutdown windows and reconnection/testing. | Included investigations, exclusions, assumed service status and required attendance. |
| Demolition and make-good | Removal limits, retention/protection, disposal, substrates and finish extent. | Quantities or boundaries priced, disposal assumptions and reinstatement method. |
| Builder's works and penetrations | Who creates, seals, fire-stops, waterproofs, certifies and finishes openings. | Each included interface, excluded specialist input and acceptance evidence. |
| Temporary works and protection | Design responsibility, loading assumptions, propping, barriers, weatherproofing and monitoring. | Temporary solution allowed, design/certification basis and site dependencies. |
| Testing and commissioning | Test standards, witnesses, records, integrated testing and failure rectification. | Tests included, third-party costs, attendance and retest assumptions. |
| Other trades and client activities | Dependencies, free-issue items, access sequence, concurrent work and information dates. | Programme assumptions, attendance, exclusions and delay sensitivity. |
A standard return schedule makes bids easier to compare and exposes differences before appointment. Ask every tenderer to respond in the same order.
Base scope, options, provisional items, allowances, preliminaries and GST basis.
A complete written list, including site conditions, quantities, access and information relied upon.
Lead time, mobilisation, duration, staging, working hours and dependencies.
Proposed supervision, key trades, specialist input and any nominated suppliers.
Clearly separated value options with scope, quality, programme and risk differences explained.
Outstanding questions, requested documents, quote validity and conditions that may change the price.
A lower bid may exclude work that another tenderer included. Build a comparison matrix showing inclusions, exclusions, assumptions, allowances and programme differences, then seek written clarification before treating prices as equivalent.
A scope brief cannot remove every change, especially where concealed conditions or design development are involved. It can reduce avoidable disputes by establishing the baseline against which a proposed change is assessed.
Closeout deliverables take time and cost money. If they first appear at the end of the project, the contractor may not have allowed for them or collected the evidence during the work.
Use these headings to start the document, then expand them to match the actual project and procurement method.
Every item should identify the area, boundary, quantity basis or drawing reference needed to find it.
State the finish, performance, evidence or acceptance check that proves the item is complete.
Check services, penetrations, protection, testing, make-good and handover between packages.
Label preliminary or unverified information and require assumptions or allowances to be returned separately.
Use the same return schedule and ensure options, exclusions and provisional items are identifiable.
Record document titles, revisions, dates, addenda and the process for tender questions.
A scope of works is a controlled description of the work package, boundaries, inclusions, exclusions, evidence, constraints, responsibilities, acceptance requirements and handover expected from the contractor.
Include the project objective, site and work areas, detailed inclusions, exclusions, existing information, access, staging, interfaces, quality requirements, quote return schedule, change process and closeout deliverables.
It gives tenderers a common set of inputs and requires assumptions, exclusions and allowances to be disclosed. That reduces hidden differences, although site discoveries, market changes and approved scope changes can still affect cost.
Where site conditions, access or measurements affect the work, a tender inspection can be important. The brief should state the inspection requirement and how tenderers must report discrepancies or information they could not verify.
An inclusion is priced work within the package; an exclusion is expressly outside it; and an assumption is a condition the tenderer has relied on when pricing. All three should be written clearly.
Use a matrix that compares each tenderer's inclusions, exclusions, assumptions, allowances, alternatives, programme and handover. Seek written clarifications before treating totals as equivalent.
SCE can review available project information, clarify the work package and interfaces, identify missing pricing inputs, and help structure a project-specific brief within SCE's agreed appointment.
Share the site, project stage, available drawings and reports, known constraints, intended work package and procurement timing. SCE can help identify which briefing inputs need to be clarified before quotes are requested.