Lane Cove School Structural Remedial Project Video
SCE Corp / Lane Cove school project video
Watch this 22-second record of selected stages from SCE’s completed structural-remedial and sewer-line works at a private school in Lane Cove, NSW.
Temporary support, structural repair and sewer replacement
The video records selected stages of the completed works. It accompanies the detailed project record covering masonry-pier movement, temporary support, controlled excavation, permanent structural repair, sewer-line replacement and reinstatement.
Coordinating building and civil work during school holidays
SCE completed the structural and sewer-line works during the December 2025 school holidays, integrating controlled excavation, structural steel, a new permanent footing, replacement pipework and reinstatement. Temporary support and an exclusion zone controlled the work around the affected pier. The structural engineer provided the design and certification for the permanent repair.
Why were the structural and sewer repairs planned together?
The investigation exposed a broken sewer line beside the affected footing zone. Repairing the visible masonry alone would not have addressed the connected ground and service conditions. SCE planned the support, excavation, permanent structural work and sewer replacement as one construction sequence before backfilling and reinstatement.
For a similar project, explore structural remedial services, underground services and our education and childcare project collection. The separate Lane Cove column and brick-pier reconstruction provides another support-and-reinstatement example.
Use the remedial planning tool to organise the condition, available reports and access constraints. Review our credentials and Lane Cove service experience, then send SCE the project details and proposed school-holiday or access window.
Lane Cove school remedial video FAQs
Explore our remedial investigation and repair questions for the evidence, design and repair-planning decisions behind this type of work.
What school-repair work does this video accompany?
The 22-second video accompanies the Lane Cove project record covering masonry-pier movement, temporary support, controlled excavation, permanent structural repair, sewer-line replacement and reinstatement.
Who was responsible for the structural design and certification?
SCE delivered and coordinated the remedial construction works. Structural design and certification remained with the appropriately qualified structural engineer.
Does the footage show the complete school condition?
No. It records selected stages of the documented project. Follow the full Lane Cove school project link for the scope and supporting construction context.
Why were the sewer and footing repairs planned together?
Controlled excavation exposed a broken sewer line in the affected footing zone. SCE coordinated temporary support, permanent structural repair, replacement pipework, backfilling and reinstatement in one sequence. The structural repair followed the engineer’s design and certification requirements.