1Boundary and public interface
Confirm the legal site boundary, adjoining buildings, public roads, footpaths, cycleways, driveways, bus stops, utilities and any land that the hoarding would occupy or overhang. Public-land use often requires a separate council or road-authority approval.
2Hazards and protection level
Assess demolition, excavation, falling-object, plant, vehicle, scaffold, crane, stored-material and unauthorised-access risks. The assessment determines whether a simple boundary barrier is enough or whether overhead and impact protection is required.
3Wind, stability and ground
Temporary fencing and hoardings can overturn or collapse if loads, fixings, bases, bracing or ground conditions are not resolved. Account for wind exposure, sheet material, gates, graphics, uneven ground, excavations and nearby services in the documented design and installation method.
4Pedestrian accessibility
Maintain a clear, stable and usable path past the site. Consider path width, kerbs, ramps, crossfalls, overhead clearance, sightlines, lighting, people using mobility aids, prams and safe separation from traffic. Any alternate route must be authorised and properly implemented.
5Site access and emergencies
Locate gates for safe deliveries and workforce access without creating uncontrolled conflicts with pedestrians or vehicles. Plan locking, after-hours security, emergency access, evacuation, fire-service needs and legible contact or warning signage.
6Traffic and visibility
Check whether the hoarding affects lanes, parking, crossings, signals, signs, intersections, driveways or loading. SafeWork NSW guidance for overhead protective structures requires visibility and line-of-sight considerations and consultation with the relevant council or road authority.
7Design and approval documents
Identify the drawings, calculations, specifications, certificates, traffic or pedestrian plans, insurance evidence, fees and bonds required by the approval authority. Preserve clear ownership between the contractor, temporary-works designer, engineer, certifier and approving authority.
8Inspection and change control
Set inspection points for installation, handover, severe weather, impact, altered access, excavation changes, scaffold changes and removal. Record defects and repairs promptly, and do not modify panels, foundations, gates, signs or loads without the required review.