New Road Construction
Plan ground preparation, drainage, pavement layers and the route to handover.
NSW civil project planning guide
Road construction is more than pavement placement. A deliverable package coordinates survey, ground conditions, drainage, services, traffic, environmental controls, materials, testing and handover.
This guide explains the planning questions clients should resolve before construction, alongside the issued design, geotechnical advice, traffic requirements, asset-owner standards and approvals. For delivery, explore SCE’s road construction services.
This guide concerns delivery of a new or reconstructed road package. Where an existing pavement is being restored rather than replaced, use SCE’s pavement rehabilitation planning guide to frame condition evidence, treatment selection, staging, testing and handover.
Start with work limits, intended use, design status and the completion standard. The package may include clearing, earthworks, subgrade, drainage, service crossings, pavement layers, kerbs, barriers, line marking, temporary access and reinstatement. Identify what is by others and who coordinates each interface.
Survey, geotechnical data, contamination information, service records, drawings, specifications and approval conditions.
Traffic, access, erosion and sediment, dust, noise, water, public separation, environmental and stakeholder requirements.
Levels, materials, compaction, layer thickness, drainage performance, finish, testing, records and asset-owner handover.

Survey should confirm alignment, levels, boundaries, tie-ins and existing features. Geotechnical information may affect stripping, excavation, fill, treatment, pavement design and groundwater controls. Where data is incomplete, the brief should state who will investigate and how unexpected material will be managed.
Underground services and overhead utilities require records, locating and protection planning. Service crossings and relocations should be coordinated with drainage and pavement levels before construction reaches the interface.
Surface falls, pits, pipes, table drains, culverts, outlets and erosion controls need to function together. Water entering pavement layers or remaining on formation can undermine performance. The sequence should provide temporary drainage during earthworks and protect completed work from uncontrolled runoff.
For connected packages, see Earthworks, Concreting and Underground Services. Explore SCE’s road and transport infrastructure capability through Roads, Highways, Bridges and Dams.

| Stage | Possible control | Record |
|---|---|---|
| Formation/subgrade | Levels, condition, proof or testing required by the specification. | Survey, inspection and test results. |
| Fill and pavement layers | Material source, moisture, thickness and compaction requirements. | Delivery records, lot tracking and test reports. |
| Drainage/services | Alignment, levels, bedding, connections and inspection before cover. | Photographs, inspections, tests and as-builts. |
| Surfacing | Preparation, weather, material, joints, thickness and finished tolerance. | Batch/delivery data, test results and survey. |
The issued specification and responsible practitioners determine the actual inspections. A generic checklist is not a substitute.
Traffic arrangements, road occupancy and public interfaces must be planned with the relevant authorities and competent traffic practitioners. Environmental controls may address sediment, erosion, dust, noise, vegetation, contaminated material, water quality and spill response. The project programme should include notifications, inspections and maintenance of temporary controls.
The Blackbutt road reconstruction was initially proposed in five stages to keep residents’ properties accessible. SCE reviewed that requirement and instead reconstructed one side of the road, then the other. The two-stage arrangement maintained access throughout and gave the construction team a more continuous work area.

When developing a road programme, identify the access that must be preserved before fixing the stage boundaries. Compare how different work areas would support both the road users and the construction sequence, with the site-specific traffic and release requirements resolved for the selected approach.
A staged opening needs its own release check. Identify the section being reopened, the remaining construction zone, temporary drainage and surface transitions, required inspections, barriers, signs and access arrangements. Allocate responsibility for checking the stage before reopening and for maintaining temporary controls until the next stage begins. Record outstanding work so a temporary opening is not confused with final handover.
Our civil access and delivery questions cover plant selection, site access and organising civil work.
Road construction can include investigations and design, earthworks, drainage, utility interfaces, pavement layers, surfacing, kerbs, barriers, signs, line marking and reinstatement. SCE brings these works together with procurement, testing, certification and handover for the agreed project. The scope needs clear work limits and responsibility for each connection and authority requirement.
Ground strength, moisture, fill, rock and groundwater can affect excavation, treatment, pavement design and construction methodology.
The applicable authority and competent traffic practitioners should confirm requirements for the project and road environment.
The inspection and test plan should define lot sizes, hold points and acceptance requirements before each layer is covered.
Locate services early and compare their alignment and levels with the road, drainage and proposed excavation. Agree protection, relocation and any required shutdown with the relevant service owner before reaching the work area. SCE coordinates those interfaces and the necessary inspections so crossings are checked and recorded before pavement construction conceals them.
Typically required evidence may include surveys, test results, material records, as-builts, approvals, inspections, defect closeout and maintenance information.
Send the location, purpose, drawings, specification, survey, geotechnical and service information, approval status, quantities and programme constraints through the website form. Include the access that residents, businesses or emergency vehicles need to retain. SCE reviews the available information and explains the design, investigation and construction steps needed for a coordinated proposal.
Identify the access that must remain available before selecting stage boundaries. At Blackbutt, SCE replaced the proposed five-stage sequence with work on one side of the road and then the other, maintaining residents’ access and giving the team a more continuous work area. Each project still needs its own traffic arrangements, inspection releases and safe transitions before a stage returns to use.
See Civil Services for broad capability and Civil Infrastructure Projects for relevant project evidence.

Plan ground preparation, drainage, pavement layers and the route to handover.

Coordinate the new pavement with the existing road, services and traffic.

Compare routine repairs with broader rehabilitation and reconstruction.
Review SCE’s service locations, company credentials and building and civil capability when assembling the project team.
SCE can develop and deliver the engineering, design, procurement and construction package, connecting pavement, drainage, services and access with testing and handover. Send the available project information and intended delivery outcome so our team can define the investigations, design decisions and construction stages needed.